Islands Trust Housing Options Toolkit, 2025                                                                                                                                                                     1 
 
TOOL 1.2 - Model LTC Major Housing Project Timeline* 
MAJOR HOUSING PROJECT TIMELINE  
Meeting
1
 Milestone Target Dates
2
 Comments Cost 
PHASE 1: PROJECT PLANNING  
1 LTC  identifies topic areas and issues, adds to work program    
 
LTC engages with First Nation governments on consultation 
approach  
   
 
LTC may engage with community to inform issues, scope and 
options  
   
2 LTC provides direction to draft Business Case July   
3 LTC endorsement of Business Case, forwarded to Committees Sept - Nov   
PHASE 2: PROJECT INITIATION - YEAR 1 
 Preliminary research and data gathering.  Jan - March   
4 
Project formal launch: communications to First Nation 
governments, landowners, stakeholders, agencies, and 
community meeting. 
April - May    
 Development of Terms of Reference for APC or working groups  April - May   
5 Endorsement of Project Charter June   
PHASE 3: ANALYSIS 
 Data gathering and research May - Sept   
 Drafting of Discussion Paper May - July   
 Special APC or Working Group appointments and referrals June   
 Preparation and analysis of data/mapping  June - July   
 LTC review of Discussion Paper(s) July - August   
PHASE 4: CONSULTATION 
 First Nation, stakeholder and public engagement  July - Dec   
 On-going analysis and revisions to data/mapping  Sept - Dec   
 
1
 Recommended to schedule special meetings for these milestones other than routine bylaw readings or LTC direction 
2
 Note: these are guidelines but timelines differ for different Local Trust Committees 

 
Islands Trust Housing Options Toolkit, 2025                                                                                                                                                                     2 
 
MAJOR HOUSING PROJECT TIMELINE  
Meeting
1
 Milestone Target Dates
2
 Comments Cost 
PHASE 5: DRAFTING  YEAR 2 
6 LTC Review of consultation results and policy options Jan - Mar   
7 Review of draft bylaw language  Feb - March   
8 Direction to prepare bylaw(s) March   
PHASE 6: LEGISLATIVE  
9 LTC Review of draft bylaws, early referrals April - June   
 Legal Review (targeted) June   
10 Community Information Meeting June   
11 Consideration of revisions and 1
st
 reading   July-August   
12 Consideration of amendments and 2
nd
 reading Sept   
13 Community Information Meeting/Public Hearing** Oct   
14 3
rd
 reading, Executive Committee, Minister of Municipal Affairs Oct - Nov   
15 Final Adoption Dec - Jan   
PHASE 7: IMPLEMENTATION 
 Procedural updates Nov - Dec   
 Bylaw amendment communication(s) Dec    
TOTAL     
 
*Refine timeline and milestones as required. Add rows as needed. 
** Under recent amendments to Local Government Act Section 464, local trust committees are prohibited from holding public hearings 
for zoning changes th

First 3,000 characters. Open the original for the whole document.

Nearby in Islands Trust Area

Browse the archive

Archive index · Full-text search · All Islands Trust Area records · All Reports & Publications